Consistent with previously described plans, today workers started delivering equipment to be used to support the repainting process.  The equipment is custom-designed and fabricated for the tower.  Assembly and pilot testing will require at least several weeks of work.  We wanted to notify the community that you may observe related activity.

Read More
Television Tower Television Tower

Update 5-5-2023

Baltimore City permit to commence work has now been issued.

Expect to see painting crews from VTS on site in the coming weeks.

Read More
Television Tower Television Tower

Update 4-13-2023

Materials and crews are expected to arrive on site the first week of May, 2023.