Update 10-6-2023

The tower has been painted up to 170 feet.

Read More
Television Tower Television Tower

Update 8-2-2023

The bottom 100 feet of the tower have been painted.

Read More
Television Tower Television Tower

Update 7-5-2023

The bottom 45 feet of the tower has been prepped and painted. The tower crew has received additional components for the containment system and will begin test fitting and installation of the next tower section this week.

Read More
Television Tower Television Tower

Update 6-13-2023

The tower crew is working to assemble the containment system near the base of the tower in order to finalize the function of the system.

Read More
Television Tower Television Tower

Update 6-7-2023

The tower crew began rigging the tower today.

Read More
Television Tower Television Tower

Update 5-18-2023

VTS has arrived on site to begin ground work on the containment system framework.

Read More
Television Tower Television Tower

Update 5-9-2023

Consistent with previously described plans, today workers started delivering equipment to be used to support the repainting process.  The equipment is custom-designed and fabricated for the tower.  Assembly and pilot testing will require at least several weeks of work.  We wanted to notify the community that you may observe related activity.

Read More
Television Tower Television Tower

Update 5-5-2023

Baltimore City permit to commence work has now been issued.

Expect to see painting crews from VTS on site in the coming weeks.

Read More
Television Tower Television Tower

Update 4-13-2023

Materials and crews are expected to arrive on site the first week of May, 2023.

Read More